|
Army Manoeuvres
Work is under way to stabilise a slope running alongside
a road used by the MoD in the west of Scotland.
A Road in mid-Argyll used by the Ministry of Defence for
critical services is undergoing repairs to its upslope to
prevent debris falling on to the road. Rock cuttings, up to
14m in height, exist on the upslope side of the road, which
is approxi mately 4km in length.
Over recent years several small slope failures have occurred
on the cuttings adjacent to the road. The developer, Turner
Estate Solutions, commissioned consultant URS to design a
solution to improve the level of safety along the entire length
of the road.
Investigation, including preliminary emergency remedial work,
was undertaken between March 2007 and March 2008, by URS'
geotechnical and soil and groundwater technical director Ermanno
Rambelli.
Its aim was to fully assess the risk of further slope failures
and to give an initial assessment of the extent of potential
work required. "Due to the nature of the rock, the gradient
of the hillside and the orientation of discontinuities within
the rock mass, extensive sections of the road cutting were
unstable and prone to failure," says Rambelli. "For
ease of management we have broken down the 4km long road into
26 smaller sections and prioritised the remedial works on
the basis of the likelihood of failure and associated risk."
As part of these initial works specialist geotechnical contractor
BAM Ritchies undertook de-vegetation, investigation and preliminary
emergency scaling work on a critical, high-priority slope.
In October 2008 URS completed the design of the remedial
works on five sections of the road considered to have the
highest priority for remediation. As part of these works,
detailed geostructural analysis of the rock mass was carried
out to assess the stability of the rock cuttings within the
top priority sections.
The design solution, which, in principle, will be common
to all the slopes to be stabilised, included de-vegetation,
slope re-profiling, scaling of loose and/or fractured rock,
rock bolting and the installation of permanent stabilisation
systems.
The systems comprise rock anchors of length and diameter
suitable to local conditions, active- tensioned facing mesh
and, where required, erosion-control matting under the facing
mesh for soil retention leading to vegetation development.
To provide value for money, the design revolves around galvanised
GEWI bars provided by Dywidag and high-strength TECCO-facing
mesh and TECMAT erosion-control matting supplied by Geobrugg.
In November 2008 BAM Ritchies commenced work on the full
stabilisation works at the first of the highest priority sections.
These works have been carried out under the supervision of
URS' Geotechnical Department.
In this section, the works comprised the full de-vegetation
of the rock face, followed by heavy scaling using excavators
and rope access personnel. Some 3,500m3 of material has been
removed and the slope re-profiled accordingly. Following the
re-profiling of the slope an active remediation system has
been installed to secure the rock face and contain further
rock slips/falls.
Within this first section, 233 rock anchors have been installed
using a combination of a drilling mast on a Merlo telehandler
and rope-supported rigs. These anchors consist of 25mm GEWI
and 30mm GEWI Plus that are galvanised for enhanced corrosion
protection.
Grout socks
Owing to the fractured nature of the Schist rock many of the
anchors have been grouted-in using grout socks to ensure that
the grout is not lost and adequately secures the bolt in the
ground. Approximately 5% of the rock anchors are pull-out
tested to ensure that the design loadings are achieved by
the rock anchors.
"The slope face has been found to be heavily fractured,
even at depth, after the slope re-profiling," says BAM
Ritchies' senior geotechnical engineer Stuart Jackman.
"The use of the grout socks is necessary to ensure no
grout wastage and to bond the rock bolts into the rock. The
rock bolt testing programme has confirmed the adequacies of
this method."
For this section 2,730m2 TECCO mesh has been installed, with
a 450m2 area of TECMAT installed for localised erosion control.
The mesh is secured to the rock anchors by the system "Spikeplates",
that ensures proper transmission of the surface loads from
the actively- tensioned mesh to the rock anchors. Boundary
ropes are used around the periphery of the treatment area
and pre-filled gabion baskets, provided by Maccaferri, placed
along the road side as a barrier between the road and the
stabilised slope.
This first phase of work has recently been completed. Work
on the next four priority sections of the road commenced on
26 January. Despite very cold weather at the end of January
and throughout early February the contractor is making good
progress and this second phase of works is due for completion
at Easter. The value of the first two phases of work is about
£900,000.
URS is designing remediation solutions for the next eight
sections of the road, with design of the remaining sections
to follow. Remediation works at these additional sections
will be awarded and started as the design is finalised and
budgets approved.
Planning and preparation for further phases of work is under
way and it is hoped that this work will commence in the new
financial year for completion by April 2010. These further
phases of work will more than double the spend to date.
Article courtesy of Ground Engineering - april 2009
Further Info
Peter Bishop - Head of Public Relations & Corporate Communication
BAM Nuttall Limited
St James House, Knoll Road, Camberley,
Surrey GU15 3XW
Tel: 01276 63484
Fax: 01276 66060
peter.bishop@bamnuttall.co.uk
|