|
Fast jack on track
The last level crossing on the West Coat Mainline
is being replaced this Easter with the help of a mighty box
jack at Tipton in the west Midlands.
This weekend a 100m section of the West Coast Main Line just
south of Birmingham will be ripped up, the embankment it runs
on will be removed and a massive 6,500t concrete box shoved
through the gap with the help of 30,000kN thrust from three
jacks. With that, it will end a 50 year effort to get rid
of the nearby level crossing on the main road into Tipton.
Sandwell Metropolitan Borough Council first started trying
to get rid of the crossing in the 1950s. It is believed to
be the last such crossing on the West Coast Main Line (WCML)
and its road barriers are down for an incredible 45 minutes
in every hour as a succession of high speed and local commuter
trains whip by. This is hardly ideal for encouraging business
into Tipton.
“Plans to put a tunnel under the railway were first
drawn up in the 1950s, when the scheme would have cost just
£500,000. It’s a bit more now,” says Sandwell
major works structures manager Irfan Choudry. Quite a lot
more, in fact.
Indeed, that the scheme is being built at all owes much to
the persistence of the council and the inventiveness of the
project team. The scheme was resurrected in 1999 as part of
the West Coast Main Line modernisation programme, when ridding
the WCML of level crossings was seen as a high priority. A
preliminary design was put together and a box jack rapidly
emerged as the best way to minimise disruption to the railway
and minimise risks from poor ground conditions.
A price of £7.8M (including £3.3M land purchase
costs) was estimated and a bid for funding was thrown together
in time for the first Local Transport Plan process in 2000.
From there, the scheme entered the Department for Transport’s
programme.
So far, so good. Once the project was in the programme, detailed
design work could start. It was here problems started to emerge.
Detailed site investigations revealed shocking ground conditions.
A fault cuts right across the site, the area used to be a
canal basin and was filled in with poor material, there are
old mine workings in the footprint of tunnel box and the whole
area is contaminated from former industrial workings. “The
ground was described as toothpaste,” says Steve Beech,
project manager for D&B contractor BAM Nuttall. “It
certainly was not exactly good materials to put a 6.5t structure
on.”
Other complications included the need to rebuild pedestrian
subways to comply with the Disability Discrimination Act,
provide new access for a boatyard and rebuild a car park.
These pushed costs to £13.5M. Nevertheless, the council
pressed on and appointed BAM Nuttall in 2003, going for the
ECI approach.
The next problem was Network Rail. “We negotiated a
tender price in 2004 but it took until 2007 to get all the
approvals,” explains Choudry. “The reason for
the delay was Network Rail. Network Rail clearly benefits
from the scheme, as the level crossing is being removed, but
its works agreement is designed for third party works –
and we wanted some balance as its original demands were very
one sided.” “Network Rail wanted the contractor
to put in place insurance for £130M, which we thought
was unheard of,” says Choudry. “We couldn’t
get more than £50M from the marketplace.” In the
end the council ended up paying Network Rail an “undisclosed
premium”.
There were also squabbles over construction methods, with
Network Rail understandably edgy about works on its railways
after the Gerrards Cross tunnel collapse (NCE 19 March). “It
took two years to get agreement,” says Choudry. “And
it’s all still in favour of Network Rail – but
we got some concessions.” The rail operator is even
footing some of the bill.
The delay pushed costs up to £17.7M and work finally
began in September 2007. Since then it has been plain sailing.
Sheet piles were driven on each side of the embankment and
16m long reinforced concrete augered piles driven to support
a casting and jacking basin. The basin has been excavated,
a steel wire anti-drag system laid, and finally the box itself
has been cast – a beast of a structure 50m long, 14m
wide, 8m deep with 950mm thick walls, floor and ceiling.
Now all the pressure is on the box jack itself. The final
Network Rail hurdles have been overcome – the proposed
methodology scored an impressive 95% in the rail operator’s
new “probability of success test” which all rail
schemes now have to satisfy after last Christmas’s Rugby
resignalling shambles.
BAM Nuttall is well versed in the art of the box jack, with
its recent success of jacking beneath a live M1 carriageway
giving confidence. This one is different. A 101 hour possession
starts tomorrow evening and the jack has to be finished when
it ends on Easter Monday.
On the M1, the box inched forward at 2.5m to 3m a shift.
Here, it will march forward at 2.5m to 3m an hour. As soon
as the overhead power lines are turned off, workers will spring
into action: track will be lifted, ballast removed, and excavators
moved into position to start digging out ahead of the box.
A full height channel will not be excavated and the box is
fitted with a cutting head so it can create its own path.
This will eliminate overdigging and minimise the amount of
backfill required. Less backfill means less chance of settlement
under the heavily skewed box.
The box will be driven along by three jacks, each connected
top and bottom to its rear end. Pretressed Macalloy bars will
hold the jacks in place at the top, each carrying 91t of load.
By hour 27, more than 10,400m3 of spoil will need to have
been excavated and by hour 35, the box should be in place
– three shifts will carry out the work.
Despite the need for speed, care and precision are required
as the overhead catenaries and cables will remain in place.
So the excavator operators will have to exercise extreme caution.
Lubrication is also allimportant. Steel ropes will be fed
along the underside of the box to help it slide, “much
like the caterpillar treads on a tank”, says Beech,
with four “treads” each with 128 ropes.
In addition, bentonite will be injected along the sides of
the box through nozzles between the box wall and the excavated
face. After jacking is complete, the bentonite will be expelled
with grout, which will also fix the box in place.
Once the box is in place, ballast must be replaced and track
relaid – and there is only a 12 hour contingency for
bad weather, breakdowns and unexpected obstructions. Best
of luck – but then with a 95% probability of success,
who needs it?
Who’s
who?
Client: Sandwell
Metropolitan Borough Council
Client’s representative: Mott
MacDonald
Design and build contractor: BAM Nuttall
Designer: Halcrow
|
Article courtesy of New Civil Engineer (09/04/2009)
Further Info
Peter Bishop - Head of Public Relations & Corporate Communication
BAM Nuttall Limited
St James House, Knoll Road, Camberley,
Surrey GU15 3XW
Tel: 01276 63484
Fax: 01276 66060
peter.bishop@bamnuttall.co.uk
|