|
Hidden Treasures
Parts of west Wales remain surprisingly remote, relying
on narrow, twisting roads that can be easily blocked. But
the £16M Llandysul bypass will help open-up Ceredigion
to access from the south and boost the local economy. Ed Owen
reports.
Ceredigion is visited all too infrequently, which is a shame
because the area has stunning, unspoiled scenery. The problem
is a perennial one in Wales - links east to west are generally
good, but links north to south have always been poor.
Ceredigion County Council principal engineer Alun Davies
explains: “We are a remote county in west Wales. Types
of industry available are limited by communications. This
road [the A486] is the vital link to the M4 corridor and is
the latest phase of a scheme to make Ceredigion better connected.
And it is a major project."
At the picturesque town of Llandysul, the problems on the
A486 are magnified. The town has narrow streets where traffic
can easily be brought to a standstill. This can affect journey
times from the important regional centre of Aberystwyth, which
has better links to the Midlands than it does to South Wales.
The solution is to simply cut out the town, creating a 3.5km
£16M bypass around it. Once complete, the route will
reward drivers with some stunning views. But this classic
scenery provides the main problems for the scheme - to create
a straight road through two river valleys.
The solution is to construct three viaducts - two 120m and
one 160m in length, and drive an alignment through a hillside.
"A better road will have a huge impact on journey times.
Llandysul is the bottleneck. If something happens in the town,
it can have a severe impact on the roads either side of it,"
says Davies. "The scheme is essential to promote the
economic prosperity of Ceredigion."
Consultant Capita Symonds won the original design tender
back in September 2000, but the project has had an unusually
long gestation period thanks to a drawn-out planning inquiry.
By the time contractor BAM Nuttall began the main works on
19 March 2008, the team had had plenty of time to refine the
project. The original design would have generated 100,000m3
of excess spoil from a total of 265,000m3 of earthworks to
create 1.5km of cutting at the northern end of the scheme.
"By changing the vertical alignment we came down to
a balanced scheme," says BAM Nuttall project manager
Ian Williams. "Initially it was left to us to re-use
material, but this change was more economical, and reduced
more than 25,000 truck journeys."
"The real problem was getting the material out, which
would have been a problem on the already congested road,"
he points out.
Secondly, the team altered the design of two of the three
major structures, from multigirder composite to ladder beam
designs. The time did not stretch far enough to re-design
the third structure, but the new structures saved some £200,000
by significantly reducing the quantity of steel required at
a time when prices were at record levels.
The three main structures sit on large abutments up to 16.4m
by 5.8m by 1m and piers up to 10.3m in height or spread foundations
to carry the new road around the town and north over the rivers.
The project was due to open in May 2010 but this date has
been brought forward to early August 2009.
Article courtesy of New Civil Engineer (19/01/09)
Further Info
Peter Bishop - Head of Public Relations & Corporate Communication
BAM Nuttall Limited
St James House, Knoll Road, Camberley,
Surrey GU15 3XW
Tel: 01276 63484
Fax: 01276 66060
peter.bishop@bamnuttall.co.uk
|