|
Cats, Dogs and Creep
Curing a sliding hillside in the Welsh Valleys meant
dealing with the slide during the works too, reports Adrian
Greeman
Contractors, like farmers, will always complain about the
rain. But main contractor Carillion and its piling subcontractor
BAM Ritchies had slightly more cause to complain than normal
during slope stabilisation work for a rail line at Sebastopol
in the Welsh valleys this summer. It rained solidly for two
months during July and August. It was, says BAM Ritchie's
senior contracts engineer Phil Howard, "just biblical".
Not only did the unprecedented downpours - the worst recorded
in South Wales - thoroughly test the drilling crews' wet weather
gear and Carillion's follow-on concrete team, but, more importantly,
tested their logistical skills and planning.
The downpours came just as the teams had a crucial six-week
railway possession, with intensive round-the-clock work needed
to complete vital piling work alongside the rail track and
construction of a concrete longitudinal capping beam, before
letting the trains restart, which they did with just hours
to spare.
Halting the slide
The piles and beam are to be the main element of new groundworks
that are intended to halt the slow slide of the hill down
the slope above the railway and into a river bed at the bottom.
Downslope creep at this point has turned into full-scale
slide several times since the single-track line was installed
in 1858 to carry millions of tonnes of high-grade steam coal
from the valley mines down to Cardiff docks for the British
Navy and the Merchant Marine.
"Among others there were major slides in 1906 and 1932,"
says project manager for client Network Rail Dan Tipper. "The
latter taking out one of two lines in the valley at the time."
Creep in recent years has been about 150mm annually on the
hillside and about 40mm at the track location, which has gradually
distorted the alignment, despite routine track maintenance.
"We have had to impose speed restrictions," says
Tipper "with the line down to 20mph [32km/h] in 2005."
Recently a 10mph [16km/h] limit has been needed on the 200m
long section.
The Cardiff-Rhymney route up through Rhymney valley remains
sufficiently important in the post-mining era to warrant significant
stabilisation works. It carries commuter traffic and is part
of efforts to keep the valleys alive, economically and socially.
Rail operator Arriva also has one of its main depots in the
valley.
Remedial work had been attempted including the use of Grundomat
driven piles in the rail cesses and dewatering installed on
the hillside to help stabilise the slope. The piles helped
for a while, but it is thought the dewatering had little impact.
"We did a small-scale trial for that," says Austin
Weltman, geotechnical director from consultant Tony Gee &
Partners which worked for Network Rail to examine the problem.
The consultant has since transferred to Carillion once the
company, which has a term works contract with Network Rail,
was asked to take on the £7.95M job.
“Although we got a lot of water there was no detectable
difference in the movement," says Weltman.
Water is important, however, he says. Monitoring has shown
a strong correlation between heavy rainfall and an accelerated
movement on the slope above the track, some two or three days
after a rainfall.
Staggered piles
With dewatering ruled out, various options were looked at
by Network Rail, working with the Environment Agency. A massive
retaining wall below the rail line was considered, but the
hill slope is steeper there and access difficult.
Toe weighting was considered the best option, but this would
have meant loading the ground at the valley bottom and shifting
the river over to do it.
Apart from environmental considerations, this option would
be difficult to execute because of the presence of an old
mine waste tip on the other side of the valley.
The eventual plan was for a staggered, twin row of piles
alongside the affected track length on the lower valley side.
These would be anchored back into the bedrock of the hillside
at a 30° angle, through a top beam along the piles.
More work was to be done further up the slope to cut through
the shear line of the slip plane and stop the movement there
by installing a grid of piles to go in the hillside.
The shear surface is about 8m-10m deep, says Weltman, sometimes
coinciding with the point where bedrock begins, although often
above it; the rockhead varies between 10m-20m deep below glacial
tills and slope debris.
Piles, a total of 178 in all, would be 16m to 23m up here
into bedrock an assortment of mudstone, siltstone and sandstone.
But first came the staggered piles for the trackside. Like
the grid piles, they are continuous flight auger (CFA) piles
600m in diameter with a hefty 16mm thick steel tube for reinforcement,
406mm in diameter. Piles were 12m-23m long depending on location,
with deeper ones needed at one end of the site where bedrock
was deeper.
Two Soilmec CF 150 machines were used to install these, working
from a 6m wide platform formed along the 200m track length
once Network Rail had removed its track during the six-week
summer possession. Two staggered rows were installed at a
1m interval to make up 259 piles.
“The rigs are very powerful," says Howard, "with
a 10t torque." The big rigs weighing 38t were chosen
over smaller machines to make sure the socket could be cut
into the bedrock and in case any large boulders were encountered;
the area is notorious for "house-size" boulders,
he says, although "We were lucky".
Even larger rigs were contemplated, but a balance had to
be struck between power and the load on the ground, since
everything was being done on essentially a live slide area.
The rigs were serviced by two cranes working on a second
platform further up the hillside, which would be used later
for the pile grid as well.
These lifted in skip loads of concrete from an agitator on
the top platform, says Carillion's project manager Andrew
Sorley. A local Tarmac plant was the supplier.
These cranes also lifted in the steel tubes once the drills
were withdrawn and these were pushed down through the fresh
concrete by a mixture of gravity and vibration from 4t units
suspended from them. Most piles needed the extra force for
the last few metres.
Heavy rain
Getting the tubes' positions correct was critical with a lateral
tolerance of 50mm and vertical tolerance of just 25mm
The rain made extra problems here too because the slide was
gently moving throughout. In the heavy rain, the top of the
slide on the hill moved as much as 300mm
"It played havoc with the setting out," says Carillion
engineer Matthew McKenzie. Survey points further away had
to be used constantly to check positions.
Some six to eight piles were completed each day, each with
about 6m3 of concrete. Following on behind came more concreting
in the nightshift as Carillion formed new sections of the
capping beam, a substantial structure 1.25m deep and 1.2m
wide. Within the beam the contractor had to form ducts for
the anchors to pass through later on.
Anchoring work came next. But most of this could be done
working from the trackside, within Vortok safety fencing and
with a carefully managed posting of lookouts and controlled
movement on site. Trains pass at about half-hour intervals
now possession has ended.
"There were a dozen or so anchors that did have to go
in during the possession because the track space narrows at
the top end of the site and the rigs had to sit on the railway
line space," says Howard.
Boom time
Trackside space was still narrow, however, for about 50% of
the remaining distance and BAM Ritchies had to use excavator-mounted
drills, Atlas Copco A65 masts on Hitachi units.
Sitting on the end of the boom, these allowed the bores to
be made back underneath the machines. Conventional rigs working
forwards were used for the rest. "We used a Casagrande
and Atlas Copco," says Howard.
Anchors were set at 30° and were between 276m and 37m
long, depending on bedrock. They were made with a 250mm diameter
bore with a 32mm tendon, with a bonding length at the end
of about 11m A sulphate-resistant cement grout filled the
bores.
While this was under way the top platform was being bored
with the CFA rigs, the pattern of piles forming a 5m by 5m
grid.
Work up here was cautious and 20 or so piles were installed
with small lighter rigs at the beginning of the job to allow
the cranes to operate and later the bigger piling rigs finishing
the job.
To guard further against potential slip movement on the hillside,
the platform was also loaded with temporary fill. This left
no space for the drill rigs and therefore a small section
of the temporary toe loading had to be constantly shifted
as the rig moved along, to create a working area.
Work has progressed swiftly and the last of the anchors were
installed in late November 2008 with only site finishing and
tidying to be completed by Carillion in December. And the
trains are back to 50mph, their old speed limit on this curving
valleyside line.
Article courtesy of Ground Engineering (Janaury 2009)
Further Info
Peter Bishop - Head of Public Relations & Corporate Communication
BAM Nuttall Limited
St James House, Knoll Road, Camberley,
Surrey GU15 3XW
Tel: 01276 63484
Fax: 01276 66060
peter.bishop@bamnuttall.co.uk
|