|
BAM delivers sub-sea electricity link
to Europe
Near Grain in north eastern Kent BAM Nuttall is partway
through a project that will see the UK plugged into mainland
Europe. Paul Thompson reports.
On a hot summer day the landscape on the Isle of Grain to
the north east of the Medway towns of Strood, Rochester, Gillingham
and Chatham is looking its brooding best.
The marshlands that inspired Victorian novelist Charles Dickens
to set part of Great Expectations in the area have a way of
making visitors feel somehow unwelcome, almost cut off from
the outside world.
But near the small town of Grain contractor BAM Nuttall is
working on a project that will do exactly the opposite and
connect this section of the garden of England to mainland
Europe. However, it is not the lure of the tourist Euro and
a second tunnel to the continent that will link the two.
Undersea cable
In keeping with much of the power-related industry the latest
link will be a giant 1000Mw capacity undersea extension cable
running between two huge electricity converter stations, the
first being built at Maasvlakte near Rotterdam in the Netherlands
and the second here at Grain.
Contractor BAM Nuttall has taken the £23m deal to build
the civils side of the UK facility under a joint venture with
electrical engineering specialist Siemens which will carry
out the electrical side of the work.
In a twist of fate BAM Nuttall's Dutch sister company BAM
Civiel is taking care of the Maasvlakte station.
BAM Nuttall project manager Jay Moorhouse is the man charged
with delivering the socket that will enable client BritNed
- a joint venture between energy transmission companies National
Grid and TenneT - to deliver its €600m sub-sea link.
Huge transformers
The transfer stations themselves each house six huge 240 tonne
transformers that will convert the direct current electricity
that passes along the 260km link between the Dutch and UK
stations back into alternating current before it passes into
the transmission networks on both sides of the North Sea.
"Alternating current loses power over distance so direct
current is more efficient. Our job is to provide a station
that can convert that back into alternating current for use
on the network," explains Moorhouse.
And part of that job is to build the twin transformer houses
which feature two 25m-high, 45m-long reinforced concrete walls,
built in three 15m bays and connected by a two-storey, steel-framed
and precast concrete-walled office and control block.
These houses will accommodate the twin cable and convert
the power as it links from the bottom of the North Sea and
into the UK network.
Towering over the rest of the site the two walls and the
smaller dwarf blast walls that jut out from them at each bay,
were slipformed by Austrian specialist Gleitbau Salzburg over
a period of four weeks.
"Each of them took about a week to set up and then a
week to pour," explains BritNed site civils manager Spencer
Pepper. "Then it was a case of moving on to the next
wall which took a similar time."
A set of hydraulic jacks set the slipform system on its way
casting the 450mm-thick wall - reinforced using 16mm-20mm
diameter rebar - at a rate of 150mm per hour.
The jacking rods were placed at 3m centres along the main
wall, 14 in total with a further two jacking rods on each
of the blast walls.
Concrete supplier Hanson Premix provided the C35 concrete
for the walls from its depot at the Grain LNG (liquefied natural
gas) terminal a few miles away and although it features plasticiser
admixtures the recipe is a fairly standard concrete, admits
Moorhouse.
"There was lots of testing carried out to make sure
we got the concrete right before the pour.
"We did trials with Gleitbau Salzburg where we set up
a pour and struck the concrete within six hours.
"Also we were fortunate that when we were pouring the
walls during March and April the weather conditions remained
constant.
"It doesn't matter whether it is hot or cold as long
as the climate remains constant.
"It means you don't have to play with the mix to accommodate
fluctuations," says Moorhouse.
Sensitive equipment
But it is the additions to the concrete reinforcing structure
and the lengths that the team have to go to in an effort to
fully insulate and protect the sensitive equipment from interference
from any external electrical fields as well as protecting
the concrete from disintegrating that set the project apart.
In the valve hall where the transformers will sit the team
needs to build a Faraday Cage - an enclosure of continuously
linked conducting material - which will protect them from
external electrical fields.
This involves sitting a copper mesh on top of the rebar cage
in the slab which then links on to the reinforcement in the
wall.
Further links from the wall into the cladding enable the
cage to be completed. And in the filter bed slabs the opposite
is the case.
These have to be fully isolated because should any electricity
discharge through the reinforcement steel the concrete could
heat up, which causes it to crack and fail.
To minimise this possibility every connection in the rebar
cage needed to be isolated using a rubber dowel bar sleeve
and then tied using plastic cable ties.
"We did look at other options including glass fibre rebar
but it was too expensive. At the moment it is almost five
times the price of steel bar so it just didn't stack up,"
says Moorhouse.
And although the laborious task of isolating each connection
meant the steel fixing for the filter beds took three weeks
to complete there was no programme impact thanks to the civils
side of the project being well on course for its December
2009 completion.
Why Kent?
"There was a great deal of time and effort spent in making
sure that we got the right location for the project,"
BritNed site manager Spencer Pepper explains.
"We had been looking for a site between Norfolk and
Kent which satisfied our requirements for the scheme."
That wish list included the close proximity of an electricity
sub-station to take the electricity out to the grid, an area
to build the converter station with a minimal amount of local
impact and also a site which boasted the geography and bathymetry
to bring the cable to shore safely.
At Grain the twin cables are to be drawn through a 250mm
diameter duct underneath a Site of Special Scientific Interest.
Areas to re-house the site's population of water voles have
also been created and it is hoped that these will be able
to receive the first of the voles later this year.
"They have been trapped and taken on holiday for a while
until their new accommodation is ready for them," says
Pepper.
Pile placement in the Isle of Grain
While the location might be excellent from a strategic point
of view the earth is not ideal for building large structures.
"The ground is not particularly favourable for us,"
says Jay Moorhouse, BAM Nuttall's project manager.
"It is a mixture of clayey alluvium and gravels."
Hence the installation of 1200, 500mm-diameter driven cast
in situ piles reaching as much as 35m through the 1.3m pile
mat and into the alluvial clay.
Prefabricated reinforcement cages from Staffordshire-based
specialist Romtech supplement the C40 concrete mix pumped
into the piles.
"It is a very good quality piling mat. 1.3m thick and
produced using 80,000 tonnes of crushed granite brought by
boat from Scotland by Bardon Aggregates," says Moorhouse.
The haul road is another area that has had to be rigidly
designed. Not your average site haul road thrown down with
some leftover hardcore this has to be able to withstand loading
from trucks weighing more than 240 tonnes as they deliver
the transformers. It is more than 600mm thick and is strengthened
by three layers of tensar geotextiles.
Fact
File
Scheme - BritNed Subsea Link - UK Converter
Station, Isle of Grain.
Client - BritNed Development - a 50:50
joint venture between National Grid and TenneT
Contractor - BAM Nuttall / Siemens
joint venture
Slipforming sub-contractor - Gleitbau
Salzburg
Project value - Overall project €600m.
UK civils package - £23m
Contract type - Bespoke Engineering,
Procurement, Construction contract
|
Article courtesy of Contract Journal - july 2009
Further Info
Peter Bishop - Head of Public Relations & Corporate Communication
BAM Nuttall Limited
St James House, Knoll Road, Camberley,
Surrey GU15 3XW
Tel: 01276 63484
Fax:01276 66060
peter.bishop@bamnuttall.co.uk
|