home

HomeAbout usSectorsHistoryNewsCareersTrainingSustainabilityRoyal BAMLocationsPrivacyLinksSearchtile

Problems And Answers
This DPC roundup of port and harbour maintenance projects and products takes us from Europe to Australia and on to the Americas - we kick off in Scotland

Rosyth has been through difficult times over the past decade. The Babcock-owned yard on the north bank of the Firth of Forth has suffered from tightening government purse-strings — but a Royal Navy contract to build two huge aircraft carriers by 2016 has transformed its prospects for the next few years.

It will also transform the historic Number 1 Dock, because current capacity is insufficient for the two 65,000-tonne 284m-long, 74m-wide, 56m-high carriers — to be named HMS Queen Elizabeth and HMS Prince of Wales.

Originally built at the beginning of the 20th century, the dock was extended in the 1960s and is long enough to accommodate the vessels, but advances in naval architecture mean that the dock's cross-section is unsuitable for modern warship building. And contractor BAM Nuttall has won an infrastructure upgrade contract worth £35M ($51M) to reconfigure the dock and to carry out work on the adjacent non-tidal basin by October 2010.

Scope
Had naval architects perpetuated the historic V-shaped warship design then it would have possible to retain the huge slabs of granite, called 'altars', that bench out from the sides of the dock and allowed ships to be propped upright while work continued. But now they have to be cut back to the same width as the top tier (coping level).

The gated dock entrance is also being widened to accommodate the ships, as is the sliding gate — from the current 38.1m to 42.1m — that separates the non-tidal main basin from the Firth of Forth.

The team will also install the 120m-span, 1,000-tonne capacity Goliath gantry crane that will straddle the dock, plus foundations for the `skidding' mechanisms that will allow shipwrights to slide the prefabricated sections of each aircraft carrier into position. Shipyards around the country are building different sections of the carriers, which will be welded together at Rosyth.

Making it happen
A total of 87 reinforced concrete 1,200mm-diameter bored piles will be positioned 3m into the underlying sandstone rock on the eastern side of the dock as foundations for the crane, while a further 295 raking piles (1-in-4) are being driven as much as 7m into a rock socket on the western side.

Even the concrete pads on the dock floor are significant pieces of engineering — they must be able to withstand the crushing force of the 65,000-tonne ships. These heavily reinforced plinths are cast in two sections with the first recessed 300mm into the dock floor. A 2m-thick slab is cast on top of them before the skidding mechanism's fixed.

As this is written, demolition and removal of the stepped granite altars is under way, with teams using a wall saw to slice through the rear of the 3-tonne Norwegian granite blocks on the line of the existing face, enabling the top row of altar stones to be removed. An excavator with a rock wheel attachment will then cut through the remaining step before the whole process is repeated.

When the team's removed them, the dock floor will be about 9m wider — but the stepped altars are also structurally important. In order to retain integrity, BAM Nuttall's drilling specialist sister company BAM Ritchies is installing 150 rock anchors up to 21m into the sides of the dock that will be then grouted into position and tensioned with a 100- tonne stressing load.

Finally...
The dock can be split into two through an intermediate gate, enabling one side to be used as a drydock while sections of the warships are floated in on the other side. The main gate to the dock is to be removed, refurbished and reused as the new gate for the direct entrance — and that alone has required temporary works (to allow dewatering of the dock mouth and direct entrance) that are themselves massive feats of engineering.

Work on the dock's entrance — and the direct entrance to the main basin — has meant building a huge cofferdam around them. "There are five 18.5m- diameter circular cells," project manager Dougie Grant told DPC, "and five arcs that link each cell."

Built using 700 tonnes of 500mm wide Arcelor steel sheet piles, the cofferdam cells were placed from a working platform floated into the main basin and backfilled using a 6E-grade granular material — about 8,000 tonnes in each. The link arcs were placed in a similar way.

They're of a size that had not been attempted for many years, but vital to the project's successful outcome.

Article courtesy of Dredging and Port Construction - march 2009


Further Info
Peter Bishop - Head of Public Relations & Corporate Communication
BAM Nuttall Limited
St James House, Knoll Road, Camberley,
Surrey GU15 3XW
Tel: 01276 63484
Fax: 01276 66060
peter.bishop@bamnuttall.co.uk

 

Removing the altars

Removing the altars will widen the docks