|
It’s a bus… on tracks
This is the story of a railway that closed because of bus
competition - only to re-emerge as a 'railway' carrying buses.
We have seen derelict railways converted to footpaths; now,
in Cambridgeshire, we are seeing a development which closely
resembles the precursor to the railways - the guided trackway.
Or in this case, the conversion of a derelict railway into
a guided busway.
The advice of the Government's CHUMMS
The passenger service on the line between Cambridge and St
Ives survived until 5th October 1970. A freight service was
retained as far as Histon but this ceased in 1983. Freight
to Fen Drayton survived until 1992 because of a long-term
aggregates contract.
Following the complete closure of the line, most of the track
remained in-situ apart from the last few miles to St Ives.
In 1994, Cambridgeshire County Council put forward a proposal
to purchase the land and the surviving track in order to restore
a passenger service. This never happened. In the late 1990s,
the Government launched the Cambridge to Huntingdon Multi-Modal
Study (CHUMMS), chiefly to address the chronic local traffic
congestion. The study suggested a guided busway along the
Cambridge-St Ives route. This would involve replacing the
track with a concrete busway and the demolition of the stations
to provide guided busway stops. Buses would travel along the
disused line, continuing through Cambridge on normal roads
and join the guided busway at Cambridge Railway Station to
travel through to Addenbrooke's Hospital and the Trumpington
Park & Ride.
Longest busway anywhere in the world
The scheme went before a public inquiry in 2004. Cambridgeshire
County Council awarded a 'Design and Build' contract to BAM
Nuttall Ltd in the summer of 2006. The detailed design of
the guided busway has been undertaken in a joint venture between
Arup and Parsons Brinkerhoff Ltd. Eventually, construction
started in 2007 with the remaining track being lifted.
So far, all of this is generally available non-technical knowledge.
But how does a guided busway work in practice. What is it
made of and how is it constructed?
Arup has been working on the project from an early stage
and has developed ideas from the few existing busway projects
around the world. In the UK there are short sections in Leeds
(11/4 miles), Crawley (250yds) and Ipswich (200yds).
In Germany, Essen has a four mile busway whilst in Adelaide,
Australia, a 71/2 mile scheme is in operation.
The Cambridge to St Ives project is by far the longest anywhere
in the world at 16 miles.
Extremely tight tolerances
Essentially, the busway is a concrete ladder made up of a
pair of precast concrete beams linked by precast concrete
spacers. All of the components are precast locally in a factory
production process. The contractor has 28 moulds and the capacity
to produce 14 ladder beams per day. The beams have a 700mm
wide bus running surface and a 180mm high guideway upstand.
They and the spacers are cast to extremely tight tolerances
in steel moulds. The ladder panels are 15m long and landed
on foundations every 71/2m. These foundations are either spread
footings or piled foundations, depending on the ground conditions.
When assembled, the space between the beams is filled with
shredded tyre rubber, top soiled and then seeded. All that
should be visible once the system has matured will be the
concrete running surface and the upstands of the beams.
In all but the tightest of curves, the individual beams units
are straight. This has not proved to be a problem at the proposed
line speed of 60mph. Neither is there any superelevation.
If horizontal curvature has to be catered for, this is done
at the casting stage by precision packing out the upstand
section of the steel moulds.
No signalling
The buses - all standard vehicles - are fitted with jockey
guide wheels which are attached to the steering track rod
ends. It is a very simple and basic system. The jockey wheel
is 90mm diameter. For the high speed running sections, there
is just +3mm tolerance in the 2,600mm gauge between guide
faces. For slow speed running, this can be relaxed to +5mm.
The guide wheel gauge is set at 2,605mm to ensure that there
is always contact between the wheels and the upstands. Essentially
a permanent engineering structure, there are facilities to
adjust top and line by jacks should this be necessary to maintain
the ride quality in the future.
At level crossings, the upstands are flared away from the
track at exit and entrance points. There are traffic light
controls which always give priority to the buses. The 'six
foot' is narrow - the desirable dimension being 800mm. It
can go down to 700mm in places.
All the system so far is double track and there is no need
for signalling. Buses drive on line of sight.
Design handbook
Kulvinder Rayat of Arup has been working on the scheme right
from the start. He was involved in the trial running on the
first section to be built. "We started running buses
at about 20mph and gradually increased the test running speed
to a maximum of 60mph. It was extremely smooth with the joints
between the sections barely detectable.'
Guided busways now have their own design handbook. Developed
by Arup for Britpave, it deals with all the aspects of busway
planning, design and construction.
The busway is due to open later this summer. With it will
come a direct link between the new housing in St Ives, the
proposed eco town in Oakington and the renowned technical
park to the north of Cambridge, with connections through to
the railway station and hospitals. The precision of the engineering
should make this project a far cry from the distant days of
wagon wheels running in stone grooves. And what did that evolve
into?!
Article courtesy of The Rail Engineer- may 2009
Further Info
Peter Bishop - Head of Public Relations & Corporate Communication
BAM Nuttall Limited
St James House, Knoll Road, Camberley,
Surrey GU15 3XW
Tel: 01276 63484
Fax:01276 66060
peter.bishop@bamnuttall.co.uk
|