|
Tunnel cure for paralysed Tipton
A £22 million scheme to replace the last level crossing
on the Euston- Wolverhampton route with a tunnel took a major
step forward over Easter with the sliding-in of a box structure
under the railway.
BAM Nuttall Ltd was awarded the contract to design and construct
a relief road in August 2007, helping ease the severe road
congestion caused by Tipton level crossing near Wolverhampton
which, during peak periods, can see the barriers lowered for
as many as 45 minutes in every hour. Due to the huge amount
of passenger and freight traffic using this corridor, it has
not been uncommon for the barriers to remain down for 20 minutes
at a time. The problem is so acute that buses are no longer
routed over the crossing for fear of being heavily delayed.
Come October, all this is set to change with the opening of
the relief road which will cross the site of the Tipton Station's
former car park before passing under the railway some 300
metres south of the present crossing, which will then close.
Also closing will be Watery Lane shunt frame which monitors
the crossing and gives the slot to Wolverhampton panel signal
box for the protecting signals. The existing pedestrian subway
under the line is to be retained and enhanced.
Three hydraulic jacking rigs
A major possession began at 0030 on Friday 9th April and,
during this time, the 6,500-tonne box - which is 58m long,
19m wide and 9m high - was slid into position using three
hydraulic jacking rigs, each with a maximum thrust of 1,200
tonnes. The maximum combined thrust used during the four days
was 2,165 tonnes.
Steve Beech, BAM Nuttall's project manager for the scheme,
explained that installing a tunnel beneath a railway is usually
the last option when all other possibilities have been explored.
"But the cost of an overbridge was prohibitive due to
the level and concentration of the neighbouring highways,
businesses and housing. Other alternatives considered included
a different location some 800 metres away but that was rejected
because the local community wanted the bridge near to the
town."
Before the box could be built on site, a casting basin had
to be constructed where, over 40 years, a long-disused canal
basin had been filled with rubbish. This was a relic of when
the main line canal branched off at this point, passing beneath
the railway.
To assist movement of the box during the operation, the tunnel
has a plated steel soffit and was constructed on top of 120
steel wire cables that were laid on the jacking slab. To help
the sliding action, grease was applied to the wire ropes and
Benotite - liquid clay – was injected into the front
of the tunnel to increase lubrication between the tunnel walls
and the embankment. In addition, as the box moved forward,
a further 512 steel wire ropes were fed under the tunnel to
form a track, ensuring that the sliding action was always
between the steel soffit plate and the greased wire ropes,
as opposed to the ground. This method allowed the box to be
jacked forward by an average of 1.7 metres every hour.
Local recreation area
The project has seen 60,000 tonnes of spoil excavated from
the site, with 50,000 tonnes of this being used to landscape
and create new playing fields for a local recreational area.
The remainder was too contaminated to be reused and has gone
to a landfill site. 12,000 tonnes was excavated during the
Easter blockade.
The line was handed back to Network Rail at 0230 on Tuesday
14th April, 21⁄2 hours ahead of schedule.
Article courtesy of The Rail Engineer - may 2009
Further Info
Peter Bishop - Head of Public Relations & Corporate Communication
BAM Nuttall Limited
St James House, Knoll Road, Camberley,
Surrey GU15 3XW
Tel: 01276 63484
Fax:01276 66060
peter.bishop@bamnuttall.co.uk
|