home

HomeAbout usSectorsHistoryNewsCareersTrainingSustainabilityRoyal BAMLocationsPrivacyLinksSearchtile

Limestone barrier protects sea town
A tourist town in mid-Wales is in the throes of a huge coastal protection scheme after winning funds from the Welsh Assembly Government.

Aberaeron is a pretty Edwardian coastal harbour town on the west
coast of mid-Wales. Sandwiched between the better known resorts of New Quay to the south and Aberystwyth a few miles north, it has basked in its unpretentious ness for more than 100 years.

Brightly coloured houses cluster around its harbour and quayside in a vista that only those tourists in the know have wit nessed over those years. But unless a bid by local authority Ceredigion County Council to stem the destructive affects the Irish Sea is having on its coastal protection structures succeeds, there may not be that much town left for tourists to visit.
Aberaeron is fortunate that it lies on the west coast of Wales. Coastal protection projects on the east coast of England have been few in recent years.

In mid-Wales it is a little different. There is a pot of funding cash from the Welsh Assembly Government waiting to be spent on these types of schemes. Richard Edwards, head of the Highways, Property and Works department at Ceredigion County Council, is aware that his project is fortunate to have won the coastal protection postcode lottery.

"This is a Welsh Assembly Government-funded scheme, not Department for Environment Food and Rural Affairs," he says. "Within Ceredigion there is a need for about £40 million to be invested in coastal protection works."

Limestone protection
Contractor BAM Nuttall has taken a £4.5 million deal with Ceredigion County Council to deliver Aberaeron's North Beach protection scheme, which will see 79,000 tonnes of locally sourced carboniferous limestone used to protect the town.

Existing wave walls will be heightened and refurbished while the beach is reprofiled and nine new greenheart timber groynes will be built out seaward from the land. In addition, site workers will build two rock groynes using the same huge 6 tonne chunks of rock that will also form a 500 m-long continuous revetment along the north side of the harbour mouth and on beyond the terraced cottages of the north part of the town. A further steel sheet pile flood wall is also being built as part of the project.

"It is a very significant scheme for Aberaeron," says Mr Edwards, "There have been times when the sea wall has threatened to breach, although it never has. There has been significant overtopping during storms and high tides and the existing groynes have deterio rated very badly. We seemed to be regularly spending £100,000 on patching and repairs to the exist ing sea wall so there was obviously a need for this scheme."

Which is where Ray Jones, BAM Nuttall site manager for the North Beach project and his team of experienced staff who will help deliver it come in. It is halfway through a 42-week delivery pro gramme for the coastal protection scheme and the local rugby club has also played its part.

Initial tenders for the scheme were based on the rocks for the revetment being delivered by sea. Unfortunately, this put the project approximately £2 million over budget and so the only option the client could consider was one where the boulders are delivered overland. A staggering 4,000 lorry movements will transfer the 6 tonne average-sized rocks from quarries around Minffordd on the edge of the Snowdonia National Park some 64 km to the north.

A temporary haul road was built through land owned by the local rugby club to serve the site and redirect the 20 tonne pay-load wagons from Aberaeron. "We were able to negotiate an alternative access along the south of the rugby pitch and down to the beach. In the end, it probably saved the scheme," says Mr Jones.

Construction of the 250m-long haul road began in December 2008 using a 600 mm-thick compacted layer of capping material and, since the first week in January, hundreds of lorries have used it. Each day 8-900 tonnes of stone have been delivered to the site and the lorries have also helped to build up a stockpile of the 79,000 tonnes of carboniferous limestone that will be used during the con struction of the rock revetments.

Rock armoury
These rocks are unloaded from the road wagons and placed in the stockpile using a 45-tonne grab. This also loads the dump trucks, which take the rocks out to the dozers and the 35-tonne grab-fit ted excavators, which place the 6 tonne rock armour.

Existing beach cobbles and pebbles are dug away to the required profile and the material stockpiled. This excavated sec tion is then covered top to bottom by a 6 m-wide strip of geotextile and the rock armour placed on top in two layers total ling 2.2 m-thick at a gradient of 1 in 2.5. This is critical to the proc-ess and the grab handler's skill is key if the huge chunks of stone are placed in the ideal three points of contact between each rock, which ensures that some of the wave's energy is absorbed by the revetment.

The stored beach material is then used to reprofile the beach at a gradient of 1 in 6.This beach will be protected by both the rock groynes, and the timber groynes, which are built using steel-tipped greenheart timber piles and whaler boards supplied from East Africa.

More than 160 of these 305 mm square section timber piles are to be driven between 4 and 8 m at 2.5 m centres into the beach using a 5 tonne drop hammer piling rig. The 225 x 150 mm whalers are butted and fixed to the northern side of each of the scheme's nine timber groynes, which stretch out some 30 to 40 m into Cardigan Bay.

The 277 m long MX16 profiled steel sheet piled wall flood defence at the northern end of the project is driven 1 to 4 m into the underly ing glacial till using a vibrating hammer. It is being shot blasted and spray-painted 'leaf green' and will be capped at the same 6 m above ordnance datum as the other structures in the scheme.

By the end of September the town will be protected from all but the freakiest of tidal events.

Cost Effective, Coast Protective

In Aberaeron a major event would mean the flooding of most of the business district and many of the homes that lie between the A487 road that slices through the town and the sea front, but the cost effective ness of protecting these properties is not the only consideration.

On most schemes funded through the Department for Environment, Food and Rural Affairs, measures are set down to assess the viability of protection schemes. These cover topics including the number of properties that will benefit by being moved out of at-risk areas and the number of low-income households that will be moved out of at-risk areas thanks to the scheme. There is also the effects the scheme will have on biodiversity.
"There hadn't been any major events here, but in terms of a tidal risk then it is entirely justified," says Mr Edwards.

"High water levels are predicted to rise around the world and flood defences around the town, which has just celebrated it bi-centenary, had deteriorated badly."

 

Article courtesy of Construction news - 07/05/09


Further Info
Peter Bishop - Head of Public Relations & Corporate Communication
BAM Nuttall Limited
St James House, Knoll Road, Camberley,
Surrey GU15 3XW
Tel: 01276 63484
Fax:01276 66060
peter.bishop@bamnuttall.co.uk

 

Scheme:
Aberaeron North Beach Coast Protection
Client: Ceredigion County Council
Consulting engineer: Atkins
Main contractor: BAM Nuttall
Contract value: £4.5million
Piling contractor: Aarsleff Piling

35-tonne grab

The 35-tonne grab fitted excavator
places the six-tonne rock armour

Aberaeron costal protection scheme

Aberaeron costal protection scheme