|
London Olympics: Cleaning up highly
contaminated land
With a higher budget than any of the venues,
the Olympic enabling works and remediation project is site
clearance on a massive scale. Andrea Klettner describes how
BAM Nuttall and Morrison cleaned up some of the most contaminated
land in modern British construction.
Mankind has inhabited East London's Lea Valley since Roman
times, with the area going through vast changes as it encompassed
life as a trade route, industrial centre and now its preparation
to become the home of the 2012 London Olympic Games.
But the area's rich history has contributed to making the
246ha site one of the most contaminated in modern British
construction, resulting in a clean-up operation of unprecedented
size.
Olympic Delivery Authority (ODA) director of infrastructure
and utilities Simon Wright explains the scale of the job 'Altogether
the enabling works and remediation have a higher budget than
any of the venues, that shows you just how big this project
is.'
The enabling works themselves have a budget of £325m,
with the total site preparation and related infrastructure
costing £1.7bn.
Because of the size of the site, the ODA decided to split
the main enabling works job, which focuses mainly on site
clearance and remediation, into two.
'It's all about risk mitigation,' says Wright. 'You have to
remember that in 2006 the market was very different and at
the time we were worried about a single firm not having enough
resources.'
In 2006, Edmund Nuttall (now BAM Nuttall) and Morrison won
the demolition and remediation contracts for the site - south
and north respectively - from the London Development Authority.
From the beginning the job proved to be a challenge, starting
with the geography of the Lea Valley. As an industrial river
basin it is criss-crossed by various waterways, railways and
the A12 artery road linking London and Essex.
BAM Nuttall engineering manager Stephen Deeble says: 'There
are lots of impenetrable boundaries on this site, making about
eight smaller island sites. 'When we first started there was
only one bridge, so one of the first things we had to do after
making the site secure was to build three more bridges to
allow us to move materials around, and for other site users
to get around more easily.'
Site surveys
Next came a series of site surveys, helping to determine where
the re-usable materials were to be found.
Morrison construction manager Aaron Evans says: 'We had a
target of re-using 90% of the waste from the site. We don't
usually get such high targets, or if we do they go out the
window because of budget constraints. 'But for the Olympics
we've been strict with sticking to them.'
Before any buildings could be demolished the asbestos was
removed and taken away from the site, leaving all other materials
to be re-used or recycled.
'The metal was all brought for recycling,' explains Deeble.'"The
masonry slabs were lifted, crushed, graded, screened and tested
for content - to be made into engineering products.'
The majority of the re-used masonry was turned into load bearing
fills to be used across the site including in temporary and
permanent roads, piling mats and fill below water level.
But the biggest job for both the southern and northern parts
of the park was still to come with the remediation phase,
with each area bringing its own challenges.
BAM Nuttall was faced with strict deadlines, having both
the main Olympic stadium and the Aquatic Centre on their half
of the site, while in the north Morrison had to contest with
an unregulated Victorian landfill.
'The excavation around the Aquatic Centre was one of the
biggest challenges,' admits Deeble. 'The site had been home
to noxious industries including tanneries and motor breakers
since the late 18th century and as it was outside the old
border of London it was not subject to any kind of environmental
constraints.'
The soil contained inorganic metals, petroleum hydrocarbons
and volatile organic compounds. 'The soil was washed and when
it was too fine to wash we bioremidiated it,' says Deeble.'"Around
the main stadium the majority of the soil was stabilised using
chemicals.
'As you can imagine, the volume of material that needed moving
was immense and we had to find temporary storage for the safe
material.'
Working together with Morrison did help here - BAM was able
to bring material to the northern part of the site to be stored
for future use, with plant mainly supplied by sub-contractor
Hawk.
Deeble continues: 'This led us to have the site for the Aquatic
Centre ready on time, and for the main stadium we were early,
allowing construction to start three months ahead of schedule.'
Thorium barrels
Meanwhile, a few kilometres to the north Morrison was contesting
with the Victorian landfill, which was rumoured to contain
thorium barrels.
'The tip made up around a quarter of our site and it was full
of historic waste,' says Evans.
A 10m-deep archaeological trench was dug around the edge
of the site. One of the most exciting things found by the
team was an old road, with evidence of an old mill.
'We also found a cobbled street, that was excavated and will
be used to build a new road in the Olympic park,' reveals
Evans.
The soil from the tip was also re-used, following a complex
sorting procedure. First, the finer soils were screened out
and the waste was handpicked. Because of the age of the tip
the majority of the waste came from wood, leather and material
sources, allowing it to be burned.
Oversized items including bottles, bricks and concrete was
crushed and re-used around the park for temporary works such
as roads and piling mats. During the process all precautions
were taken to ensure the site remained safe in the event that
thorium was found, but luckily the soil contained no radioactive
material.
Throughout the project both teams have kept a close eye on
dust control. The sheer size of the site, and the fact that
it is surrounded by residential areas, meant that local councils
enforced strict policies when it came to dust. "We started
setting up contact with the Environment Agency in 2006 and
prepared a code of practice that was incorporated into the
planning process," explains Deeble. 'Once we started
with remediation it helped that the largest muckshift we did,
for the main stadium, began in the winter when it's easier
for the soil to retain water.
'We also ensure that the stockpiles were shaped smoothly
so we didn't get wind shear, and the long-term piles are sprayed
with sealant.' Three years on from the start of the job, the
remediation is now largely finished - the teams have handed
over some 285 sites out of 350. Now BAM Nuttall and Morrison
are now working with other contractors on the site to ensure
their soil is up to standard.
Evans explains:'"We assess arisings that come from other
construction projects, then make them into fill materials.
There has definitely been a change in emphasis of our role,
we're seeing that materials are being re-used several times
over.'
Cleaning up the groundwater
The 2012 Olympic site has become the location of an innovative
trial to get rid of ammonia in contaminated groundwater.
Single-celled micro-organisms known as archaea, which occur
naturally in water and degrade ammonia in order to survive,
have been encouraged to breed on the site.
'We have produced a bioreactor so they can breed more rapidly
and extract ammonia from the groundwater,' explains Deeble.
'So far they have generated a notable improvement in ammonia
levels, and everyone knows that ammonia is notoriously hard
to get rid of.'
The water is also pumped from the ground to be treated. Some
contaminants can be dissolved and removed, while others are
eliminated through chemical oxidation.
Learning from the project
Brownfield site development is becoming increasingly more
popular in the UK, especially with the Government's ambitious
housing targets.
ODA director of utilities and infrastructure Simon Wright
believes the huge remediation job at the East London Olympic
site can serve as a blueprint for future projects, including
the Thames Gateway.
He says: 'If we are going to redevelop urban areas and avoid
building on greenfield sites, then we will certainly be dealing
with contaminated land. And the efficiency with which you
can make such land fit for re-use is vital.'
Remediation
by Numbers
Nearly 3,000 site investigations
More than 200 buildings demolished
Seven steel-framed buildings reclaimed for re-use elsewhere
97% of materials by weight arising from demolition works
reclaimed or recycled
Around 150,000 yellow stock bricks reclaimed
0.6 million m3 of material treated
More than 90% of contaminated material treated and re-used
4ha of Japanese Knotweed present on site has been chemically
treated 2.5km temporary construction roads constructed
140 archaeology trenches |
Article courtesy of Contract Journal - september 2009
Further Info
Peter Bishop - Head of Public Relations & Corporate Communication
BAM Nuttall Limited
St James House, Knoll Road, Camberley,
Surrey GU15 3XW
Tel: 01276 63484
Fax:01276 66060
peter.bishop@bamnuttall.co.uk
|